Unofficial Shuttle Launch Schedule - Full List Until About 2010
Next launch scheduled:
STS-125 Atlantis (HST-SM-4), Pad A Feb , 2009 (HST Servicing Mission 4)
Upcoming Shuttle Missions:
STS-125 Atlantis (HST-SM-4) Pad A Feb , 2009 (HST Servicing Mission 4)
STS-119 Discovery (ISS-28) Pad A Feb 12, 2008 (ISS-28-15A: PM S6, Solar Arrays/Batteries)
STS-127 Endeavour (ISS-29) Pad A May 15, 2009 (ISS-29-2J/A: JEM EF, ELM ES, SLP-D2)
*** Established Six Person Crew Capability ***
STS-128 Atlantis (ISS-30) Pad A Jul 30, 2009 (ISS-30-17A: MPLM, LMC, TVIS2, CHeCS 2)
STS-129 Discovery (ISS-31) Oct 15, 2009 (ISS-31-ULF3: MPLM, ELC1, ELC2)
STS-130 Endeavour (ISS-32) Dec 10, 2009 (ISS-32-20A: Node 3)
STS-131 Atlantis (ISS-33) Feb 11, 2010 (ISS-33-19A: MPLM, LMC)
STS-132 Discovery (ISS-34) Apr 8, 2010 (ISS-34-ULF4: MPLM, ICC, MRM1)
STS-133 Endeavour (ISS-35) May 31, 2010 (ISS-35-ULF5: MPLM, ELC3, ELC4)
*** ISS Assembly Complete ***
NOTE:
This schedule was prepared from various and partly discordant
Nasa and other sources, so it should be taken with appropriate care.
Actual launch dates are set at the Flight Readiness Review
held about two weeks prior to launch.
International Space Station (ISS) flies in an orbit inclined 51.60 degrees
to Earth's equator, while the Hubble Space Telescope (HST) is in a 28.47 degrees
inclined orbit.
Orbiter assignments as well as approximate dates are increasingly uncertain with
later times, the later STS numbers are not yet assigned and inofficial guesses.
Remember: Everything in shuttle schedules is subject to continuous revision.